In the baseline length procedure, the survey begins at an established PRS62 control point and ends at a PRS92 control point. This statement is true or false?

Prepare for the DMC Administrative Order Test No. 2007-29. Use flashcards, interactive quizzes, and detailed explanations for each question to enhance your understanding. Master the content with our comprehensive practice material and succeed!

Multiple Choice

In the baseline length procedure, the survey begins at an established PRS62 control point and ends at a PRS92 control point. This statement is true or false?

Explanation:
Baseline length procedure is used to connect the old PRS62 system to the newer PRS92 system by measuring a baseline that runs from a PRS62 control point to a PRS92 control point. This direct link between datums provides the reference distance and orientation needed to compute how coordinates shift when moving from PRS62 to PRS92. Therefore, the survey begins at an established PRS62 control point and ends at a PRS92 control point.

Baseline length procedure is used to connect the old PRS62 system to the newer PRS92 system by measuring a baseline that runs from a PRS62 control point to a PRS92 control point. This direct link between datums provides the reference distance and orientation needed to compute how coordinates shift when moving from PRS62 to PRS92. Therefore, the survey begins at an established PRS62 control point and ends at a PRS92 control point.